Simulation 03 — Permitting Time Map
How long will
permits take?
Municipal review is the largest schedule variable in a wireless rollout. Federal FCC shot clocks set 60 days for collocation on an existing structure and 90 days for a new structure; local zoning windows sit on top of those federal limits and vary by state and site type.
Jurisdiction profile
Click a state
Macro tower (SUP/zoning)—
Small cell (ROW)—
EV charging—
Commercial solar—
◆ Typical administrative review windows from program experience — individual jurisdictions within a state vary widely (shot-clock rules, hearing calendars, moratoria). Typical windows for planning only. Actual review times are set locally and confirmed per jurisdiction.
In short
- FCC Declaratory Ruling 18-133 sets a 60-day shot clock for small wireless collocation on an existing structure.
- The same ruling sets a 90-day shot clock for deployment on a new structure.
- FCC shot clocks cover all steps of the siting process, including pre-application procedures and rights-of-way agreements.
- Local zoning review windows vary by state and site type and are estimated here for planning purposes only.