Who owns what, and what is already promised
Boundary, encumbrances, easements and encroachments. Existing easements can sterilise the part of a parcel a building or generator yard needs, and they are cheap to find early and expensive to find late.
Simulation 11 — Data Center Site Readiness
Answer nine questions about a parcel and get back a readiness profile plus the order the outstanding items should be settled in. Two of the nine routinely govern the whole schedule; the rest can run in parallel. Everything is computed in your browser and nothing is sent.
Readiness profile
◆ Screening tool for early planning, computed in your browser. It is not sealed engineering, it does not constitute due diligence, and it cannot tell you whether a permit will be approved.
The nine items, in full
The same nine categories the tool asks about, written out. Two of them — electric service and the entitlement path — routinely govern a data center schedule on their own. The rest can be run in parallel once the parcel is under control.
Boundary, encumbrances, easements and encroachments. Existing easements can sterilise the part of a parcel a building or generator yard needs, and they are cheap to find early and expensive to find late.
Whether the parcel sits inside city limits, inside a city's extraterritorial jurisdiction, or in an unincorporated county. Texas counties generally hold no zoning authority in unincorporated areas, but still administer platting, floodplain development and access permits.
Large loads enter a study and interconnection process that runs on its own clock, independent of land approvals. A parcel can look attractive and still be years from the capacity it needs. Filing late is the most expensive sequencing error available on a data center site.
Whether diverse fiber routes actually reach the parcel, who owns them, and what a lateral would cost. A carrier's presence in the county is not the same as a route to the fence line.
Bearing capacity and foundation implications for heavy floor loads. Much of the Houston region sits on expansive clay, which is a recognised data center geotechnical issue and belongs in due diligence rather than in a change order.
Environmental site assessment and whatever it escalates into. Findings here can add both time and conditions to every approval downstream.
Floodplain status, wetlands and waters determinations, detention obligations and outfall rights. These constrain the developable area, which means they constrain layout — so they belong before layout, not after.
Driveway permits, roadway classification, turning movements and TxDOT coordination where the site touches a state roadway. Construction traffic is a different problem from operational traffic and both have to work.
Service availability, district boundaries and capacity commitments. Cooling approach changes how much this matters, but availability has to be established either way.
In short